The Chief Information Officer (CIO) wants to implement a redundant server location to which the production server images can be moved within 48 hours and services can be quickly restored, in case of a catastrophic failure of the primary datacenter's HVAC. Which of the following can be implemented?

The Chief Information Officer (CIO) wants to implement a redundant server location to which the production server images can be moved within 48 hours and services can be quickly restored, in case of a catastrophic failure of the primary datacenter's HVAC. Which of the following can be implemented?




A. Cold site
B. Load balancing
C. Warm site
D. Hot site


Answer: C